In his original Answer to my noble friend Lady Jones, the Minister mentioned that the Government were looking for alternative markets to replace the Chinese market as the current receptacle for much waste. Is it not immoral to say that we are just going to look for another place in the world to dump the rubbish that we should be looking after ourselves?
In his original Answer to my noble friend Lady Jones, the Minister mentioned that the Government were looking for alternative markets to replace the Chinese market as the current receptacle for much waste. Is it not immoral to say that we are just going to look for another place in the world to dump the rubbish that we should be looking after ourselves?
My Lords, there obviously need to be alternatives and we are looking at them. Nothing is exported in the way that the noble Lord describes—there are very strong and strict requirements. I agree with him about wanting to recycle more at home but a number of countries—Turkey, Taiwan, Vietnam and India—all have resources and are taking more waste. However, we certainly want to work more on recycling at home.
To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 10 February (HL5652), what (1) proportion, and (2) volume, of excavated spoil from each of the HS2 Phase 1 construction sites will be transported from them by (a) rail, (b) road, and (c) river.
To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 10 February (HL5652), what (1) proportion, and (2) volume, of excavated spoil from each of the HS2 Phase 1 construction sites will be transported from them by (a) rail, (b) road, and (c) river.
Excavated material arising from the construction of Phase One of HS2 will be transported along the construction corridor (site haul) where it is reasonably practicable to do so. Where that is not possible, or for movement along longer distances, the material will be transported by public highway, along designated routes. Where reasonably practicable, rail has been considered for the transportation of large quantities of excavated material over long distances. There are currently no plans to move any of the excavated material by river.
The approximate quantities and relative proportion of each of these transportation methods, allocated to broad sections of the proposed route is set out in the table below. These figures reflect the assumptions reported in the Environmental Statement deposited alongside the Phase One Bill and, as such, are a plausible worst case in terms of both total volume of excavated material and proportion transport by highway and rail. The project has made a commitment to maximise the amount of excavated material transported by rail and are working to increase the proportion transport by rail and decrease the proportion transported by highway wherever reasonably practicable.
(All figures are in million tons and movements may include multiple handling)
| Site Haul | Public Highway Haul | Rail Haul |
Central London & Metropolitan area | 16.9 (56%) | 4 (13%) | 9.46 (31%) |
Buckinghamshire Northants & Warwickshire Country areas | 72.4 (80%) | 17.9 (20%) | - (0%) |
West Midlands Metropolitan area | 29.9 (61%) | 18.9 (39%) | - (0%) |
Total Phase One Routewide | 119.2 (70%) | 40.8 (24%) | 9.46 (6%) |
To ask Her Majesty’s Government what (1) proportion, and (2) volume, of excavated spoil from each of the Thames Tideway Tunnel construction sites will be transported from them by river.
To ask Her Majesty’s Government what (1) proportion, and (2) volume, of excavated spoil from each of the Thames Tideway Tunnel construction sites will be transported from them by river.
The Development Consent Order for the Thames Tideway Tunnel (TTT) requires 100% of the specified materials to be transported by river for construction sites on the Thames foreshore, unless an approved derogation is in place. Derogations could include periods when it is not possible to use river transport due to factors such as river closures, incidents, weather and supply chain failures, and for material not suitable for river transport such as contaminated material that needs specialist disposal or material that is too wet for safe transit without specialist vessels.
The commitment to transportation by river from the construction sites was secured through the River Transport Strategy, which was included in Thames Water’s application for Development Consent for the Tunnel, although it only applies to specific material listed in the Strategy (including excavated material from the main tunnel at main tunnel drive sites and material excavated from the shafts at foreshore sites).
Bazalgette Tunnel Limited (operating as Tideway), the company appointed to design, finance, build and operate the TTT, has estimated the proportion and volume of excavated spoil that will be transported by river from each of the TTT construction foreshore sites (see Table 1 below). The percentages shown for each site demonstrate the anticipated effect of derogations on the amounts of excavated spoil they will be able to transport by river.
However, Tideway and appointed mains works contractors have made commitments to maximise their use of river transport and are therefore working on opportunities to increase the extent of river transport further in liaison with the Local Authorities, Greater London Authority, Port of London Authority and Transport for London.
Table 1 - Excavated specified material percentage and volume by river transport
SITE | % of all excavated specified material transported by river | Volume to be transported by river (m3) |
Putney Bridge Foreshore | 90% | 14,000 |
Carnwath Road Riverside | 90% | 353,400 |
Cremorne Wharf Depot | 90% | 9,000 |
Chelsea Embankment | 90% | 44,400 |
Kirtling Street | 81% | 693,600 * |
Heathwall Pumping Station | 82% | 16,300** |
Albert Embankment | 90% | 56,300 |
Victoria Embankment | 90% | 27,900 |
Blackfriars Bridge | 90% | 72,100 |
Chambers Wharf | 90% | 416,100 |
King Edward Memorial Park | 90% | 57,500 |
*excludes shaft and excavated material from ‘other' minor structures, due to restricted river frontage
**excludes 'excavated material from ‘other' minor structures', due to site constraints
To ask Her Majesty's Government further to the Written Answer by Lord Adonis on 15 December 2009 (WA 215), what are the estimated peak volume and peak number of lorries per day required to remove the excavated material from the central stations and shafts for the Crossrail project.
To ask Her Majesty's Government further to the Written Answer by Lord Adonis on 15 December 2009 (WA 215), what are the estimated peak volume and peak number of lorries per day required to remove the excavated material from the central stations and shafts for the Crossrail project.
To ask Her Majesty's Government when the haulage contracts for removing material and waste from excavations for Crossrail will be let; and whether the haulage contractors will be responsible for the testing for contaminated waste.
To ask Her Majesty's Government when the haulage contracts for removing material and waste from excavations for Crossrail will be let; and whether the haulage contractors will be responsible for the testing for contaminated waste.
To ask Her Majesty's Government in respect of excavated material and waste arising from the excavations for Crossrail, (a) what is the total and maximum daily expected output from each removal site, and (b) when the maximum outputs occur.
To ask Her Majesty's Government in respect of excavated material and waste arising from the excavations for Crossrail, (a) what is the total and maximum daily expected output from each removal site, and (b) when the maximum outputs occur.
To ask Her Majesty's Government what are the expected destinations and means of transport from each removal site of excavated waste and material from Crossrail.
To ask Her Majesty's Government what are the expected destinations and means of transport from each removal site of excavated waste and material from Crossrail.
To ask Her Majesty's Government how materials from excavations for Crossrail will be tested to check for contamination; where; and by whom.
To ask Her Majesty's Government how materials from excavations for Crossrail will be tested to check for contamination; where; and by whom.
To ask Her Majesty's Government how much steel waste from excavations for Crossrail is estimated to come from sprayed concrete lining waste; and whether that will be disposed of in the bird sanctuary at Wallasea Island.
To ask Her Majesty's Government how much steel waste from excavations for Crossrail is estimated to come from sprayed concrete lining waste; and whether that will be disposed of in the bird sanctuary at Wallasea Island.
To ask Her Majesty's Government what progress has been made in using biomass from waste food or crops to provide power for the Olympic Park at Stratford.
To ask Her Majesty's Government what progress has been made in using biomass from waste food or crops to provide power for the Olympic Park at Stratford.
To ask Her Majesty's Government further to the Written Answer by Lord Adonis on 24 November (WA 255-56), how much contaminated and non-contaminated soil and waste material has been removed from the Stratford Olympic Park site (a) by rail, (b) by road and (c) by water.
To ask Her Majesty's Government further to the Written Answer by Lord Adonis on 24 November (WA 255-56), how much contaminated and non-contaminated soil and waste material has been removed from the Stratford Olympic Park site (a) by rail, (b) by road and (c) by water.
asked Her Majesty's Government:Why the Olympic Delivery Authority charges £6 per tonne of spoil removed from the Stratford Olympic site by rail.
asked Her Majesty's Government:Why the Olympic Delivery Authority charges £6 per tonne of spoil removed from the Stratford Olympic site by rail.
asked Her Majesty's Government:How much spoil is planned to be removed from the Stratford Olympic site (a) by rail, (b) by road, and (c) by water.
asked Her Majesty's Government:How much spoil is planned to be removed from the Stratford Olympic site (a) by rail, (b) by road, and (c) by water.
asked Her Majesty's Government:What are the main locations of spoil arising from tunnel and station construction of the Crossrail project; and what proportion of such spoil is planned to be removed by road, rail or water; and
asked Her Majesty's Government:What are the main locations of spoil arising from tunnel and station construction of the Crossrail project; and what proportion of such spoil is planned to be removed by road, rail or water; and
What assurances the promoters of the Crossrail project have given them about the removal of excavated material from tunnels and stations by rail or water.
What assurances the promoters of the Crossrail project have given them about the removal of excavated material from tunnels and stations by rail or water.