Written question asked by Angus Robertson (Scottish National Party) on Tuesday, 25 February 2014, in the House of Commons. It was due for an answer on Thursday, 27 February 2014. It was answered by Philip Dunne (Conservative) on Monday, 3 March 2014 on behalf of the Ministry of Defence.


Cryptography

Question

To ask the Secretary of State for Defence how much his Department has spent on the Cipher project to date.

Answer

The total cost of the CIPHER project was £46 million. Work ceased in June 2013 following the Assessment Phase which concluded that the project would not meet the full defence capability required to offer long term value for money.

The work carried out during the CIPHER Assessment Phase is being used to inform necessary future work to allow the capability to be met.


Secondary information

Type
Written question
Reference
189467; 576 c718W
Session
2013-14
Subjects
Defence Costs Cryptography
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk